Guide
Change request template for agencies and freelancers
A one-page change request to copy, a filled-in sample that adds one feature and drops another, a change log and two emails.
By Vincent Trienpont · Published · Last checked · 8 min read · How we write
This change request template is a one-page document you send when a client asks for work outside the signed scope. It names the change, its price, its effect on the deadline and what happens if the client says no, and it ends with a line to approve it. Below: the template to copy, a filled-in sample that adds one feature and drops another, a change log to keep beside it, and the two emails that go with it.
When to use a change request
A change request is for one specific addition or change during a project that has a signed scope. It is the document that turns "can you also…" into a decision the client makes with the price in front of them. If you are still deciding whether a request counts as extra at all, start with how to handle scope creep without losing the client: it sorts requests into favours, change requests and new projects, and gives you the replies for each.
Use this template when the answer is "yes, that is extra". It only works if your scope said what was in and what was out. Writing a scope of work a client can count covers that part: counted deliverables, an out-of-scope list and the assumptions behind the price.
A change request is not a new proposal. If the request is a project in its own right, with its own goal, a different team or a budget bigger than the original, send a separate proposal after the current work is done.
What goes on a change request
Keep it to one page. The client should be able to read it on a phone between meetings and reply "approved".
| Field | What to write | Why it matters |
|---|---|---|
| Number and date | CR-03, and the day you send it | Every later email can point to one document |
| Project and signed scope | The project name and the version of the scope it changes | Shows what this is measured against |
| Requested by | Name and role at the client | The person asking is not always the person who approves |
| The change | What will be done, in countable terms | "One booking reminder by text message", not "SMS functionality" |
| Why | The client's reason, in their words | Shows you listened, and helps a second approver say yes |
| What it touches | Deliverables, milestones and anything that comes out | A swap is visible here |
| Price | Hours times your rate for extra work, or a fixed price | One line per part, so the client sees what drives it |
| Effect on the date | Working days added, and the new date | The cost clients forget to ask about |
| If you say no | What happens instead | Makes "no" a real option, not an awkward one |
| Approval | Name, date, and "approved" or a signature | Nothing starts without it |
Two choices sit behind the price line.
Hours or a fixed price. On a fixed-price project, a fixed price for each change keeps the deal the same shape. On time and materials, the client already carries the hours, so a change request there is an estimate with a cap they approve, not a price. Either way, use the rate for extra work you put in the proposal.
Adding or swapping. Many clients want the new thing but not the new invoice. A swap answers that: name a piece of work of similar size that comes out, put its value as a credit on the same change request, and show the net. The client decides with both sides in view.
I put my hourly rate for work outside the proposal in the proposal itself, because extra requests will come. The change request then has nothing new to negotiate: only the hours.
A sample change request, filled in
The agency, the client and the amounts are made up for this sample. Replace them with your own.
Example
CR-03 · Lantern Digital for Merrow Dental Group · sent Thursday 12 March 2026
Project: new website with online booking. Signed scope: version 2, dated 9 February 2026. Fixed price €22,000 excluding VAT. Extra work: €90 an hour excluding VAT. Launch: Friday 24 April 2026.
Requested by: Priya Shah, practice manager, on the call of 10 March.
The change. Add a text-message reminder the day before each booked appointment, using the booking system the practice already pays for. One message template, in English, editable by the practice.
Why. "Missed appointments cost us more than anything else on this site."
What it touches. The booking milestone. To keep the budget close to the original, the newsletter sign-up page comes out of this phase; the practice will add it later through its mailing tool.
| Item | Hours | Amount (excl. VAT) |
|---|---|---|
| Reminder: set-up and message template | 6 | €540 |
| Reminder: connection to the booking system | 9 | €810 |
| Reminder: testing with the practice | 3 | €270 |
| Credit: newsletter sign-up page removed | -5 | -€450 |
| Total | 13 | €1,170 |
Effect on the date. Two working days. Launch moves from Friday 24 April to Tuesday 28 April 2026.
If you say no. Nothing changes: launch stays on 24 April with the newsletter page, and we can quote the reminder again after launch.
Approval. Reply "CR-03 approved" or sign below by Tuesday 17 March, and we start on Wednesday 18 March.
The project after approval.
| Amount (excl. VAT) | |
|---|---|
| Signed scope, version 2 | €22,000 |
| CR-01, extra page template (approved 20 February) | €630 |
| CR-03, text reminders with newsletter page removed | €1,170 |
| Total | €23,800 |
Look at what makes this one easy to approve. The client sees three priced parts, a credit for the page that comes out and one net amount. The deadline moves by a named number of days, not "a little". And the "if you say no" line tells them the project is safe either way, which takes the pressure out of the decision.
The CR-02 gap in the numbering is deliberate: CR-02 was refused, and it stays in the log as refused. Numbers are never reused.
A change log to keep beside it
The change log is one table per project. It answers the question every project gets near the end: "what did we actually agree?" Send it with each new change request, or attach it to the final invoice.
Template
Change log · [Project] · signed scope version [n], [date]
| CR | Date sent | Change | Price (excl. VAT) | Days | Status | Approved by, date |
|---|---|---|---|---|---|---|
| CR-01 | [date] | [one line] | [amount] | [+n] | Approved | [name, date] |
| CR-02 | [date] | [one line] | [amount] | [+n] | Refused | [name, date] |
| CR-03 | [date] | [one line, including what came out] | [net amount] | [+n] | Waiting | – |
Agreed so far: signed price [amount] + approved changes [amount] = [new total], excluding VAT. Launch: [current date].
At my agency, a client once signed a version with our old, cheaper rates. Several versions were going round and prices were updated by hand. Numbered change requests and one log are the cure for that: there is only ever one current scope, and anyone can see how it got there.
The template to copy
Template
CR-[number] · [Your company] for [Client] · sent [date]
Project: [name]. Signed scope: version [n], dated [date]. [Fixed price / estimate] [amount] excluding VAT. Extra work: [rate] an hour excluding VAT. Current deadline: [date].
Requested by: [name, role], on [date / call / email].
The change: [what will be done, in countable terms: how many pages, templates, rounds, languages, messages].
Why: [the client's reason, in their words].
What it touches: [deliverables and milestones]. [If a swap: "To keep the budget close to the original, [item] comes out of this phase."]
| Item | Hours | Amount (excl. VAT) |
|---|---|---|
| [Part 1] | [h] | [amount] |
| [Part 2] | [h] | [amount] |
| [Credit: item removed, if any] | [-h] | [-amount] |
| Total | [h] | [net amount] |
Effect on the date: [n] working days. [Deadline] moves from [date] to [date].
If you say no: [what happens instead, for example "nothing changes; we can quote it again after launch"].
Approval: reply "CR-[number] approved" or sign below by [date], and we start on [date].
Name: ____________ Role: ____________ Date: ____________
Two emails to send with it
Template
Sending the change request Subject: [Project]: CR-[number], [change in four words] Hi [name], thanks for the idea on [day]. It is outside the scope we signed, so I've written it up as change request CR-[number], attached. In short: [change], [net amount] excluding VAT, and [deadline] moves to [date]. If you'd rather keep the date, the request also shows what happens if you say no. A reply with "CR-[number] approved" is enough to start.
After approval Subject: Re: [Project]: CR-[number] approved Hi [name], thanks, CR-[number] is approved and in the plan. We start on [date], and the deadline is now [date]. The updated change log is attached: [new total] excluding VAT agreed so far.
If a client asks for the change on a call, send the change request within two working days anyway. A verbal yes on a call is the easiest thing for both sides to remember differently.
This is general information, not legal or tax advice. For your situation, ask a lawyer or accountant.
How Propozit helps
Propozit has no separate change-request form. Before a proposal is signed, your client can select Ask for a change beside Sign: you get an email, and the proposal shows Change requested. You then publish a new version with a note, and the earlier versions stay in the history. Once a proposal is signed it is read-only, so for a change during the project, send a short new proposal for that change. Start it from the client and their details fill in, then price the change as its own line; an hourly rate for extra work shows as "Billed as used", outside the totals.
Your client signs in the deck, drawn or typed, and both sides get a signed PDF of what was agreed: see signing in the deck and send and sign. Propozit does not track hours or keep a change log for you; the table above still does that job.
Propozit is in early access and free to start.
Related
- Scope creep: how to handle it without losing the client A decision table for every extra request, a priced change request worked through in euros, and four replies to copy.
- How to write a scope of work clients understand The parts of a clear scope of work, how to make every deliverable countable, and how to handle change requests without arguments.
- Fixed price vs time and materials for agencies The same project priced as a fixed fee and as time and materials: what the client pays when the work runs short or long, a decision table and clauses to copy.
Proposals your clients actually say yes to
Propozit is free to start, with no card needed. Create your account today and see the plans on the pricing page.